The usual numbers

Under the residential codes Idaho and California adopt, a guard is required where a walking surface is 30 inches or more above the floor or grade below. Residential guards are a minimum of 36 inches high; commercial guards are 42. The assembly has to resist a load applied at the top, and openings cannot pass a 4-inch sphere.

Glass requirements

Railing glass is safety glass: tempered or laminated. Frameless guards with no top rail, where the glass itself is the structural element, are generally required to be laminated so a broken panel stays in place. Guards with a continuous top rail can often use tempered. Panel thickness depends on span and mounting.

Why your inspector decides

Those are the usual numbers, not a promise about your project. Height, whether a top rail is required, and tempered versus laminated are set by the authority having jurisdiction, and it varies between Ada County, Canyon County, the Bay Area cities and San Diego. We confirm before fabricating, not after.

Mounting systems

Base shoe along the bottom edge is the cleanest look and puts the most load into the structure. Standoffs through the face of the glass need the holes drilled before tempering. Posts with glass infill spread the load and suit older decks. Which one depends on what is under the deck or stair.

More guides

Questions

Questions we get.

Can I put a glass railing on an existing deck?

Usually, but the deck decides which system. A base shoe needs solid framing underneath; posts or spigots spread the load on an older deck.

Do the panels have holes drilled in them?

Only standoff systems, and only before tempering. Tempered glass cannot be drilled afterward.

How long does a railing take?

Longer than a shower. Laminated glass and structural hardware run longer lead times, and exterior work can need an inspection. Plan on several weeks from final measurement.

Recent work

Recent work.

Frameless enclosure with solid brass hardware against dark teal glazed subway tile
Teal subway, solid brassSatin brass
Book-matched marble corner
Book-matched marble cornerSatin brass
Frameless corner enclosure with a transom panel on white picket tile beside a soaking tub
Picket tile with transomChampagne bronze
Frameless glass panel on a charcoal tiled walk-in shower with a lit niche and bench
Charcoal walk-inMatte black
Floor-to-ceiling frameless panel on a blue-green tiled walk-in shower with black sconces
Blue-green walk-inMatte black
Frameless corner shower enclosure with matte black hardware beside a freestanding tub
White tile cornerMatte black
Next step

Send a photo.
Get a number.

Text (208) 286-1285 a photo of the space with a rough width and height, or use the form. We come back with a ballpark, then measure and send a written proposal. We will beat a comparable quote more often than not; send it over and ask.

Text a photo Call Boise